  • Introduction

Introduction

This operation is carried out after the liquid line cool-down has been completed. The user is tasked with performing the initial two hours of the LNG loading operation. During this operation, the user ramps up the flow from the shore and loads LNG into the cargo tanks in stages. The goal is to increase the flow from 0 to 10,000 m³ per hour while ensuring that the tank levels are staggered so that all tanks do not reach their full capacity at the same time.

LNG is loaded via the loading manifolds to the liquid header and then to each tank filling valve. The boil-off and displaced vapour leave each tank via the vapour domes to the vapour header. The vapour is initially free-flowed to shore via the vapour crossover manifold and, as tank pressure rises, one compressor is brought into operation to increase the gas flow to shore and limit the vapour main and hence cargo tanks’ pressure.

De-ballasting is undertaken at the same time as cargo loading, and the de-ballasting sequence is arranged to keep the vessel within the required limits of draught, trim, stress, and stability. If necessary, the flow of nitrogen to the inter-barrier spaces is increased to maintain a positive pressure in these spaces during the completion of cool-down and the start of loading. This is often achieved by increasing the pressure in the inter-barrier spaces before starting the operation.

The cofferdam heating system is put into operation well in advance and before arrival at the terminal; e.g. when low atmospheric temperature on arrival at the port system must be set in operation well in advance. The open sea system is always in operation, to maintain steady temperatures at cofferdams and dome spaces.

On completion of loading, the liquid header and other liquid pipes are drained usually to the aft cargo tank. The liquid remaining in the inclined part of the liquid manifolds is pushed in board using N2 pressure from shore and the loading arms are then purged and disconnected.

Preparations for Loading
Loading is commenced after the cool-down of the cargo piping with one of the shore pumps. This can be done by opening the ESD and double shut valves, allowing liquid to flow directly into the main liquid lines or by opening the ESD valve and crossing over into the smaller spray line and then back to the liquid line inboard of the double shut valve. The latter system has the advantage of restricting the flow of liquid from the shore as it passes into the smaller-diameter spray line. In either case, the liquid flows initially to the end tanks (1 and 4) and then to all tanks.

Once the ship and shore pipelines have cooled down (about 90 minutes), open all tank filling valves and commence loading at the agreed rate. Loading rates are usually increased (ramped up) in agreed increments to the maximum loading rate in about one hour or as per the pump-up plan.

As the loading rate increases, it is important to monitor the evolution of the tank pressures and to start one or two HD compressors in order to limit the pressure in the tanks. If the compressors are unable to cope with the volume of boil-off and displaced gas, it will be necessary to reduce the loading rate.

During the time of cooling down of the piping and the start of loading, it is important to patrol the whole deck area to monitor for all potential cargo leaks. All leaks, even the smallest one, must be corrected immediately even if this requires slowing down or even stopping the loading.

Precautions during the early stages of loading
The initial loading rate should be at the terminal minimum rate or at a rate, which is within the capabilities of the vessel’s vapour control equipment. The rate can then be increased gradually to the maximum agreed rate where the tank pressures can be maintained steady at a working level sufficiently below the relief valve setting;

The boil-off and displaced vapour are initially free-flowed to shore via the vapour crossover manifold and, as tank pressure rises, one HD compressor is brought into operation to increase the gas flow to shore. Under these conditions, the loading rate is governed by the rate at which the terminal can handle the vapour;

In the early stages of loading, the cargo tanks and/or the incoming cargo liquid may be warm and generate vapour in excess of the vapour return line capacity. A close watch must be kept on cargo tank pressures;

The loading rate must be reduced in good time before nearing the relief valve set pressures;
LNG High Duty Compressors should be immediately available with enough electrical power available to ensure immediate starting. HD compressors should be cooled down and the lube oil warmed up prior to normal use.

If reducing the rate or the use of High Duty Compressors does not control the pressure rise, the loading must be stopped immediately and the terminal notified. In some occasions when the shore/ terminal cannot control the BOG return, then and after agreement Gas burning shall be commenced.

Loading Operation
The terminal will connect the shore loading and vapor arms to the vessel’s manifold. The ship-to-shore Emergency Shutdown (ESD) cable will be connected and the integrity confirmed. The loading and vapour arms and connections to the vessel will be leak tested to the agreed pressure and checked for leaks. A warm ESD and cold ESD test will be carried out complying with the agreed procedure.
LNG is loaded via the liquid crossover manifolds to the cargo liquid line and then to each cargo tank branch and filling valves. The boil-off and displaced vapour leave each cargo tank via the gas domes to the cargo vapour line. The vapour is initially free-flowed to the terminal via the vapour crossover manifold. As the tank pressure rises, one or both of the HD compressors are brought into operation to increase the gas flow to the terminal and limit the cargo tank pressure. Deballasting is undertaken at the same time as cargo loading and the deballasting sequence is arranged to keep the vessel within the required limits of draught, trim, stress and stability. Deballasting should be completed before the end of loading.

The nitrogen pressurisation system for the insulation spaces would normally be in automatic operation and lined-up to supply the additional nitrogen necessary to compensate for the contraction from cooling the tanks.

The cofferdam heating system should be in operation and working correctly. On completion of loading, the cargo liquid line and other liquid lines are drained to the No.4 cargo tank. The liquid remaining in the inclined part of the liquid manifolds is pushed inboard using nitrogen pressure from the terminal, and the shore arms are then purged and disconnected.

Allowance must be made when topping off the No.4 tank for cargo arms and lines draining back to this tank to prevent overfilling the tank.

It is important to remember:

  • Request terminal control to start loading at the pre-arranged reduced rate.
  • Initially, BOG returned to Shore by free flow method. As tank pressure increases start the first HD compressor to return Gas at Shore. But before starting inform the terminal and the E/R.
  • There is a great possibility to put in service the 2nd HD compressor for the first hours of loading until the pressure stabilize in normal operating levels.
  • Providing that no problems occur (such as cargo leakages, HD compressor working condition, N2 supply etc.) request the terminal to increase the loading rate up to maximum over the pre-arranged time scale.
  • Start the second HD compressor as boil-off generation begins to exceed the capacity of the first HD compressor in the service unit. Again, inform terminal control and the E/R before starting.
  • Adjust loading valve opening to provide the desired stagger between the tanks.
  • Attention to be given to the notice(s) given to terminals regarding increased/reduced loading rates.

Exercise Overview:

  1. Initial Setup:

The exercise begins with the setup of necessary systems and machinery, including Starting the required equipment. Configuring various systems. Lining up the valves to direct LNG into the cargo tanks.

  1. Assessment Process:
  • The assessment begins when the user presses the “Start Loading” button.
  • The user must ramp up the flow from the shore in increments of 1,000 m³ per hour, ultimately achieving a total flow of 10,000 m³ per hour.
  • During the assessment, the user must manage the loading process carefully to ensure that the tank levels are staggered. This means monitoring and adjusting the flow to ensure that no two tanks are filled simultaneously.
  1. Completion Criteria:
  • The exercise progresses as the user successfully completes milestones, including:
  • Correctly increasing the flow rate.
  • Achieving the required staggered tank levels.
  • The exercise is considered complete once the user has successfully achieved all the milestones, ensuring that the correct procedures were followed for flow rate increase and tank staggering.
  1. Evaluation:
  • The user’s performance is assessed based on their ability to respond to various remarks, Cautions, and alarms that occur during the course of the exercise.

 

logo

© 2026 Avrio. All rights reserved

  • Home
  • Courses
  • Our Story
  • Privacy Policy
  • Reach Us
  • Blogs
  • Terms & Conditions
logo
  • Home
  • Courses
  • Our Story
  • Privacy Policy
  • Reach Us
  • Blogs
  • Terms & Conditions

© 2026 Avrio. All rights reserved