| Alarm Condition | Alarm Time | Alarm Level | Alarm Title | Alarm Description | Action |
| When prerequisite milestones for starting the cooldown are completed. | Before Starting Cooldown | Remark | Begin the cooldown process with a low flow rate. | Begin the cooldown with a low flow of 25 m³/h. | |
| Tank Middle Temp <= 5°C | When particular tank middle sensor temperature reaches 5°C | Remark | Reduce Master Valve Opening In CT 1,2,3,4 | Reduce the master valve opening to at least 25% For CT1 and 50% For CT2,CT3,CT4. | |
| Valve not closed to required percentage, after receiving the remark | After 1 minute of receiving the remark alarm | Caution | Reduce Master Valve Opening In CT 1,2,3,4 | Reduce the master valve opening to at least 25% For CT1 and 50% For CT2,CT3,CT4. | |
| Tank Middle Temp <= 0°C | When particular tank middle sensor temperature reaches 0°C | Remark | Close One Nozzle In CT 1,2,3,4. | Close one spray nozzle in cargo tank 1 and continue cooldown. | |
| One Nozzle Not Closed After Receiving the Remark(And Action Not Taken). | 5 minutes after receiving the remark | Low Priority | Close One Nozzle In CT 1,2,3,4. | Close one spray nozzle in cargo tank 1 and continue cooldown. | |
| One Nozzle Not Closed After Receiving the low priority (And Action Not Taken). | 5 minutes after receiving the low priority | High Priority | Close One Nozzle In CT 1,2,3,4. | Close one spray nozzle in cargo tank 1 and continue cooldown. | |
| whenever temperature drop exceeds the max level. | Whenever the drop is more than -17°C during stage 1 or 11°C during stage 2. | Caution | High Temperature drop in CT1,2,3,4. | High temperature drop in CT1,2,3,4, Adjust master valve CS103,203,303,403 or reduce the flow from shore. | |
| Cargo Tank Pressure >= 14kpa | Caution | Start HD Compressor | High pressure inside the tanks, start the hd compressor. | ||
| Cargo Tank Pressure >= 14.5 Kpa | Caution | Increase HD Compressor Veins | High pressure inside the tanks,increase the hd compressor veins to maintain pressure. | ||
| Cargo Tank Pressure >= 15Kpa | Caution | Start Another HD Compressor | Start another hd compressor, reduce the veins of HD Compressor 1 before starting another hd compressor. | ||
| Cargo Tank Pressure 15.5 Kpa | Caution | Increase The Veins Of Both The HD Compressors | High pressure inside the tanks, increase the veins of both hd compressors to maintain pressure. |
Step By Step Procedure
Prepare Both HD Compressors and Required Generators for Use
Connect Manifold Arm Spool Piece
Complete the Line-Up by Following the Required Steps
| Position | Description | Valve |
| Open | No.1 cargo tank vapour valves | CG100, CG101 |
| Open | No.2 cargo tank vapour valves | CG200, CG201 |
| Open | No.3 cargo tank vapour valves | CG300, CG301 |
| Open | No.4 cargo tank vapour valves | CG400, CG401 |
| Position | Description | Valve |
| Open | Vapour line to No.1 vent mast valve | CG701 |
| Close & Auto | No.1 vent mast regulating valve | CG702 |
| Position | Description | Valve |
| Open | No.3 port cooling down valve | CS031 |
| Open | Spray line crossover isolation valve | CS072 |
| Open | Spray line isolation valves | CS700, CS701 |
| Position | Description | Valve |
| Open | No.1 cargo tank spray master valve | CS103 |
| Open | No.1 cargo tank spray rail valves | CS107, CS108 |
| Open | No.2 cargo tank spray master valve | CS203 |
| Open | No.2 cargo tank spray rail valves | CS207, CS208 |
| Open | No.3 cargo tank spray master valve | CS303 |
| Open | No.3 cargo tank spray rail valves | CS307, CS308 |
| Open | No.4 cargo tank spray master valve | CS403 |
| Open | No.4 cargo tank spray rail valves | CS407, CS408 |
| Open | No.3 cargo tank spray block valve | CS320 |
| Open | No.4 cargo tank spray block valve | CS420 |
| Position | Description | Valve |
| Open | No.1 HD compressor inlet valve | CG903 |
| Open & Auto | No.1 HD compressor surge valve | CG1021 |
| Open | No.1 HD compressor outlet valve | CG915 |
| Open | No.2 HD compressor inlet valve | CG904 |
| Open & Auto | No.2 HD compressor surge valve | CG1022 |
| Open | No.2 HD compressor outlet valve | CG916 |
| Open | Compressor line valve to vapour manifold | CG900 |
| Position | Description | Valve |
| Open | Vapour line valve to HD compressors | CG704 |
| Open | Port vapour manifold ESD valve | CG071 |
| Position | Description | Valve |
| Open | No.3 port cargo liquid manifold ESD valve | CL031 |
Note: The user must ensure that the above valves are set correctly across the various pages for proper line-up.
Note: Valve CG702 is only available in the Cargo System page.
Starting the Cooldown Process
HD Compressor Requirements
Achieve Required Temperatures Inside the Tanks
Completion of Exercise