Loading...
  • HOME
  • COURSES
  • OUR STORY
  • BLOGS
  • REACH US
  • LOGIN
  • HOME
  • COURSES
  • MY LEARNINGS
  • REACH US
  • LOG OUT

Let's get started!

Forgot Password?
Sign In

Enquiry Form

Submit
  • success stories
  • Introduction

Introduction

The purpose of the initial cooling down is to place the cargo tanks in a suitable cold condition for loading LNG. The initial cooling down must be gradually undertaken to reduce the cargo tanks’ temperature down to cryogenic temperature to:

  • Avoid thermal shock on heavy structure such as pump tower and equipment.
  • Limit the amount of vapour generation during loading.
  • Limit the nitrogen flow rate in the Interbarrier Spaces (IBS) during loading.

The initial cooling down normally follows immediately on from the gassing-up operation and is achieved using LNG supplied from the terminal. This is delivered to the spray line and is sprayed into each cargo tank, which will cool down the cargo tank and surrounding insulation. A large amount of vapour will be generated and this is returned to the terminal by using the High Duty (HD) compressors.

The rate of cooling down the cargo tanks is pre-calculated and this, along with the terminal’s ability to receive the returning vapours, are the time limiting factors. The cooling down rate with the amount of LNG required is presented to the vessel in a tabulated format.

To control the spray rate according to the cargo tank pressure, the spray lines are adjusted by the operator to achieve the cooling down schedule. The spray line pressure supplied from terminal is to the vessel’s request.

Initial starting up

On initial start-up, the requested pressure should be low in order to permit gradual cooling down of the cargo tank and structures. Once the spray line and rail and line are cooled, shown by frosting on the spray line into each cargo tank, the pressure can be increased to full pressure.

During cooling down, nitrogen flow to the IBS will significantly increase. It is essential that the rate of cooling down is controlled so that it remains within the limits of the nitrogen system to maintain the IBS pressure.

Cooling down of the cargo tanks is considered complete when the temperature sensors in each tank indicate the target average temperature. When this average temperature has been reached, and the Custody Transfer System (CTS) registers the presence of liquid, bulk loading can begin.

Vapour generated during the cooling down of the cargo tanks is returned to the terminal via the HD compressors and the vapour manifold.

Once the cooling down is complete and loading has commenced, the cargo tank membrane will be at or near to the cargo temperature, but it will take some hours to establish fully cooled down temperature gradients through the insulation. Consequently, boil-off from the cargo will be higher than normal during the first 3-4 days after loading to fully cool all of the cargo tank insulation to the loaded voyage operating temperature.

During the cooling down of the cargo tanks, cooling down the cargo lines can be undertaken. The purpose of cooling down lines is to slowly reduce the line temperature to a cryogenic level to avoid thermal shock, prior to loading LNG.

Once the cooling down of the cargo tanks is nearing completion, cooling down the lines can start, this includes the liquid manifold crossovers, cargo liquid line and filling lines to be used for loading.

It is achieved by the terminal supply of LNG being partially diverted from the spray line into the manifold crossover valves to the cool down valves on each manifold and through the double-shut valves, crossover lines and along the liquid lines to the cargo tank filling lines and valves.

As LNG slowly fills the lines the temperature probes at the manifold crossover and forward and aft sections of the liquid line should be carefully monitored for temperature drop and subsequent frosting.

Filling valves to the cargo tanks should be adjusted accordingly to ensure that there is a minimum flow through the valves to permit excess vapor out and allow the liquid line to fill and cool.

Exercise Description

This exercise focuses on the operation of cooling down cargo tanks onboard an LNG carrier. The exercise begins with all tanks in a “gassed-up” condition, where the atmosphere inside the tanks is fully filled with LNG vapor.

Exercise Overview:

  1. Initial Setup:

Liquid LNG is introduced from the shore and directed toward the cargo tanks via spray lines, which contain spray nozzles inside the tanks. The LNG is sprayed into the tanks, gradually lowering the temperature. The goal is to reach a loading temperature of -130°C inside all cargo tanks. The vapor pressure inside the tanks is released to the shore using the high-duty compressor (HD compressor) onboard.

  1. System Preparation:

Prepare the high-duty compressor and generators for operation. Connect the manifold arms and hoses (referred to as “spool pieces”). Ensure the correct valves are lined up to direct the LNG into the tanks via the spray lines.

  1. Assessment Process:

The assessment begins once the lineup is complete and all equipment is ready for operation. The LNG flow is started from the shore, and the user must achieve a temperature of -130°C inside the tanks. Throughout the assessment, the user must maintain the correct LNG flow in order to achieve the temperature drop in the requisite time period and respond to any rising tank pressure by operating the HD compressor appropriately.

  1. Completion Criteria:

The exercise is considered complete when the target temperature of -130°C is reached inside all cargo tanks within the stipulated time. The user is assessed based on their response to various remarks, cautions, and alarms presented during the exercise.

logo

© 2026 Avrio. All rights reserved

  • Home
  • Courses
  • Our Story
  • Privacy Policy
  • Reach Us
  • Blogs
  • Terms & Conditions
logo
  • Home
  • Courses
  • Our Story
  • Privacy Policy
  • Reach Us
  • Blogs
  • Terms & Conditions

© 2026 Avrio. All rights reserved